Fall Foliage, Ovando, Montana

GRIP 2 – System Modernization

This material is based upon work supported by the U.S. Department of Energy’s Grid Deployment Office, Award Number DE-GD000925.

Project Introduction

The U.S. Department of Energy’s Grid Deployment Office is administering a $10.5 billion investment via the Grid Resilience and Innovation Partnerships (GRIP) program. This historic investment will enhance grid flexibility, improve the resilience of the power system against growing threats of extreme weather and climate change, and ensure American communities have access to affordable, reliable, and clean electricity.

Project Description

There are two primary threats to the resilience of MEC’s system. The first threat is the trending rise in wildfires in the northwest, which have the potential to wreak havoc on the Cooperative’s distribution infrastructure. The second threat is the increased frequency, severity and unpredictability of storms due to the ever-changing climate.

Missoula Electric Cooperative’s Strategic Distribution System Modernization for Resilience and Wildfire Safety project seeks to build an intelligent network of high-voltage overcurrent devices that can be operated remotely based on data gathered by weather monitoring devices strategically located throughout MEC’s service territory. Reclosers can be reconfigured from normal to non-reclose during periods of elevated fire risk.

Benefits

The project will mitigate the risk of system-caused wildfires and shield the system from extreme weather events. These upgrades will protect the Cooperative’s high-risk communities, improve the system’s integrity and greatly reduce unintended outages during fire season.

Communities and Members Impacted

The project will benefit all MEC members, as it covers the Cooperative’s entire seven-district service territory.

Preliminary project map showing proposed grant locations. Locations are subject to change as necessary.

Timeline

The Strategic Distribution System Modernization for Resilience & Wildfire Safety project will use a phased approach from 2025 – 2028:

  • Design & Permitting: Currently in progress
  • Procurement: Scheduled for late 2024
  • Construction: Phased construction from 2025 to 2028
  • Operation: Phased implementation from 2025 to 2028

Procurement

Materials rfp package request

GRIP 2 RFP_Clarifications_QandA.xlsx

For the Materials RFP, MEC seeks competitive bids for the supply of materials required to implement the GRIP 2 – System Modernization project. All materials purchased under this RFP must comply with the Build America, Buy America Act (BABAA). Please click the link above to request an RFP.

Clarification Questions Due: 09/15/2026 4:00pm MT

Submission Deadline: 09/25/2026 4:00pm MT

Project Completion Target: October 2029

Questions and Clarifications

Answers for questions submitted through TBD

Contractor rfp Package Request

For the Contractor RFP, MEC seeks competitive bids for construction services to implement the GRIP 2 – System Modernization project. Please click the link above to request an RFP.

Clarification Questions Due: TBD

Submission Deadline: TBD

Project Completion Target: TBD

Project Overview

Download the Project Overview here.

Contact Information

General Project Inquiries:

Mick Aho, Integrated Services Manager

Micka@meccoop.com

406.541.6375